 |

home:
success stories:
Polk IGCC Power Plant
Tampa Electric's successful 250 MW coal gasification power
plant project near Tampa,
Florida.
Project Objective
To demonstrate IGCC technology in a greenfield commercial
electric utility application at the 250 MW size using an
entrained-flow, oxygen-blown gasifier with full heat recovery,
conventional cold-gas cleanup, and an advanced gas turbine
with nitrogen injection for power augmentation and NOx
control.
Technology and Project Description
Coal/water slurry and oxygen are reacted at high temperature
and pressure to produce a medium-Btu syngas in a Texaco
gasifier. Molten ash flows out of the bottom of the gasifier
into a water-filled sump where it is forms a solid slag. The
syngas moves from the gasifier to a high-temperature
heat-recovery unit, which cools the syngas while generating
high-pressure steam. The cooled gases flow to a water wash for
particulate removal. Next, a COS hydrolysis reactor converts
one of the sulfur species in the gas to a form that is more
easily removed. The syngas is then further cooled before
entering a conventional amine sulfur removal system. The amine
system keeps SO2 emissions below 0.15 lb/106 Btu (97%
capture). The cleaned gases are then reheated and routed to a
combined-cycle system for power generation.
A GE MS 7001FA gas turbine generates 192 MWe. Thermal NOx is
controlled to below 0.27 lb/106 Btu by injecting nitrogen. A
steam turbine uses steam produced by cooling the syngas and
superheated with the combustion turbine exhaust gases in the
HRSG to produce an additional 124 MWe. The plant heat rate is
9,350 Btu/kWh (HHV).
Results Summary: Environmental
-
The Polk Plant is one of the cleanest coal-based
power generation facilities in the world.
-
Emissions of SO2, NOx, and particulates are well
below the regulatory limits set for the Polk plant site.
-
SO2 reduction of 95% achieved.
Results Summary: Operational
-
The gasifier operated more than 29,000 hours and
processed coal at a rate of 2,300 tons/day, while the
combustion turbine operated over 28,000 hours to produce over
8.6 million MWh of electricity on syngas.
-
Power production met the target goal of 250 MWe
at a high stream factor and plant availability.
-
Carbon burnout exceeds 95%.
-
During the fourth and fifth year of operation,
the gasifier capacity factor was 75% and 66%, respectively.
For these same years, the gasifier availability was 88.7% and
84.2%, respectively.
-
For the fourth and fifth year of operation, the
air separation unit had an availability of 93.9% and 90.5%,
respectively, and the power block had an availability of 86.6%
and 93.9%, respectively.
Results Summary: Economic
-
The total cost of the Tampa Electric IGCC Project
is $303 million, or $1,213/kW. The total project cost includes
the cost of operating the unit throughout the demonstration
period as well as experimental work on hot gas cleanup. The
investment for a commercial unit would be significantly lower
than that of the Tampa project.
Project Summary
The Tampa Electric IGCC project conducted at Polk Power
Station has successfully demonstrated the commercial
application of Texaco coal gasification in conjunction with
electric power generation. Power production met the target
goal of 250 MWe at a high stream factor and plant
availability. The gasifier operated more than 29,000 hours and
processed coal at a rate of 2,300 tons/day, while the
combustion turbine operated over 28,000 hours to produce over
8.6 million MWh of electricity on syngas. Carbon burnout
exceeds 95%, and emissions of SO2, NOx, and particulates are
well below the regulatory limits set for the Polk plant site.
Along with other IGCC demonstrations in the CCT Program, the
Polk Plant is one of the cleanest coal-based power generation
facilities in the world.
Environmental Performance
The Tampa Electric IGCC Project has very low pollution
impacts. Environmental considerations have been a major
driving force from the inception of the project. The site was
selected by an independent Community Siting Task Force
commissioned by Tampa Electric. Members included
environmentalists, educators, economists, and community
leaders. Economic factors were also considered. The Task Force
evaluated 35 sites in six counties and recommended three in
south western Polk County that had previously been mined for
phosphate.
About one-third of the site is used for power generation
facilities. Another third, about 1500 acres, is used to
enhance the environment by creation of public fishing lakes
for the Florida Fish and Game Commission. This area was
converted from phosphate mining spoils to wetlands and
uplands, thereby providing habitat for native plants and
animals, and was transferred to the Commission in 1997. The
final third of the site is used primarily for access and to
provide a visual buffer. The site contains an 850-acre cooling
reservoir.
The permitted stack emissions are shown in Exhibit 33. The
plant achieved SO2 reduction of 95%. A COS hydrolysis unit was
installed in 1999 to reduce SO2 emissions, enabling the
station to meet recent, more stringent restrictions. Injecting
nitrogen into the gas turbine is used to control NOx
emissions. The use of nitrogen that would otherwise be vented
represents a novel approach in oxygen-blown gasification
technology.
A brine concentration unit processes "grey" water discharged
from the gas cleanup systems, recovering a reusable water
stream for slurry preparation and a land-fillable solid waste
stream. There is no liquid effluent. Makeup water for the
power plant is provided from on-site wells. All process water
is recycled.
Operational Performance
As originally envisioned, the overall process scheme was to
have incorporated hot gas cleanup on a portion of the raw
syngas stream. After some initial test work, support for this
option was discontinued. The cleaned syngas is sent to the
General Electric model MS 7001FA gas combustion turbine.
Nitrogen from the air separation unit (at 98% purity) is mixed
with the syngas at the combustor inlet. Nitrogen addition has
important benefits to the power plant: (1) the increased mass
flow through the gas turbine produces more power than without
the nitrogen; (2) the overall efficiency of the system is
enhanced; (3) NOx emissions are reduced; and (4) the need for
steam or water injection is eliminated.
During the fourth and fifth year of operation, the gasifier
capacity factor was 75% and 66%, respectively. For these same
years, the gasifier availability was 88.7% and 84.2%,
respectively. For the fourth and fifth year of operation, the
air separation unit (ASU) had an availability of 93.9% and
90.5%, respectively, and the power block had an availability
of 86.6% and 93.9%, respectively. The lower availability of
the gasifier in the fifth year of operation reflects the
longer planned outage in that year to replace the refractory
liner. Also, there was a
28-day forced outage to weld repair the main compressor in the
ASU.
Several modifications to the original design and procedures
were required to achieve the high availability that has been
demonstrated. Soon after initial startup, ash plugging caused
failure of some exchangers in the high-temperature heat
recovery system. This led to serious damage to the combustion
turbine. The exchangers were removed in 1997, and compensating
adjustments were made in the rest of the heat recovery system.
Additional particulate removal was provided to protect the
turbine.
Pluggage in another bank of exchangers in the high-temperature
heat recovery system was arrested by a design modification in
1999. In late 1997, hot restart procedures were implemented.
These eliminated the need to change burners and reheat the
gasifier every time it shut down, reducing gasifier restart
time by over 18 hours.
Initially, there were problems with the gasifier, which is 50%
larger than any previous Texaco gasifier. Carbon conversion in
this larger gasifier was lower than expected, and refractory
life has been identified as a significant issue. Liner
replacement is expensive and requires considerable downtime.
To achieve the target life of two years, the gasifier is being
operated at a lower temperature than design, which in turn
results in a further decrease in carbon conversion efficiency.
This caused load restrictions due to capacity limitations in
the fines handling system. A slag crusher and a duplicate
fines handling system installed in 1998 solved this problem.
Thermocouple replacement in the gasifier also presents a
problem. Replacement is relatively expensive. Thermocouple
failure by shearing is attributed to expansion of dissimilar
materials. In early 1998, revised operating procedures were
developed to handle high shell temperatures in the dome of the
radiant syngas cooler. This problem had caused two extended
outages.
Numerous short forced outages occurred in 1997 and 1998 due to
erosion and corrosion in the process water and coal/water
slurry piping systems, pumps, and valves. Various changes have
virtually eliminated these problems, and no such outages
occurred in 1999. Some of the corrective actions taken to
solve operating and maintenance problems in this project have
resulted in patent applications.
The overall heat rate of the plant is 9,350 Btu/kWh (36.5%
efficiency, HHV). The efficiency is somewhat lower than design
because of removal of the high-temperature exchangers, lower
than excepted carbon conversion, and a compressor failure in
the brine concentration unit which necessitates its operation
as a single effect evaporator. In the second half of 2000, a
slag recovery system was commissioned to recover and use the
unconverted carbon, and the brine concentration unit will be
restored to its original more efficient vapor compression
cycle. Ways are being evaluated to use the heat available as a
result of removing the high temperature exchangers. Together,
these projects are expected to increase the efficiency to 38%
(9,000 Btu/kWh), consistent with the original design value.
The IGCC's oxygen plant requires 11.5 x 106 scfm of air to
produce enough oxygen for full load operation on a variety of
fuels over the normal ambient temperature range and to
simultaneously reprocess enough fines to generate a slag
product suitable for the cement industry. This air requirement
is 8.5% above the ASU design values. The main air compressor
(MAC) could almost meet this air requirement when the
compressor was new, the MAC output has deteriorated at a rate
of about 2% per year. At the end of the demonstration period.
The MAC is 15% deficient on a normal Florida summer day. About
30% of the deficiency is attributable to pluggage of the MAC
aftercooler and resulting backpressure. The after- cooler
bundle will be replaced and all carbon steel parts coated to
prevent further deterioration. The remaining 70% of the loss
is distributed throughout the compressor system and there are
no obvious ways to resolve the deficiency.
Ten coals and blends were tested in the three
years of operation to determine the impact of feedstock
properties on system performance. These coals included
Kentucky No. 9, Kentucky No. 11, two Illinois No. 6 coals, and
three Pittsburgh No. 8 coals. Four areas were evaluated for
each coal: (1) feasibility of processing into a high
concentration slurry, (2) carbon conversion, (3)
aggressiveness of the slag to the gasifier's refractory liner,
and (4) tendency toward fouling of the syngas coolers. All of
the coals were found to be suitable with some design
modifications. Lower cost petroleum coke blends were also
tested.
Economic Performance
The total cost of the Tampa Electric IGCC Project is $303
million, or $1,213/kW. The total project cost includes the
cost of operating the unit throughout the demonstration period
as well as experimental work on hot gas cleanup. The
investment for a commercial unit would be significantly lower
than that of the Tampa project.
The Department of Energy estimates that future IGCC power
plants, based on mature and improved technology, will cost in
the range of $900–1,250/kW (1999$) depending on the degree to
which existing equipment and infra- structure can be utilized.
Heat rate ultimately is expected to be in the range of
7,000–7,500 Btu/kWh (46–49%; HHV).
Commercial Applications
The project was presented the 1997 Powerplant Award by Power
magazine. In 1996 the project received the Association of
Builders and Contractors award for construction quality.
Several awards were presented for using an innovative siting
process: 1993 Ecological Society of America Corporate Award,
1993 Timer Powers Conflict Resolution Award from the State of
Florida, and the 1991 Florida Audubon Society Corporate Award.
As a result of the Polk Power Station demonstration,
Texaco-based IGCC can be considered commercially and
environmentally suitable for electric power generation
utilizing a wide variety of feedstocks. Sulfur capture for the
project is greater than 98%, while NOx emissions reductions
are 90% those of a conventional pulverized coal-fired power
plant. The integration and control approaches utilized at Polk
can also be applied in IGCC projects using different
gasification technologies.
TECO Energy is not only actively working with Texaco to
commercialize the technology in the United States but also has
been contacted by European power producers to discuss possible
technical assistance on using the gasifier technology.
Contacts
Mark Hornick
General Manager, Polk Power Station
TECO Energy
P.O. Box 111
Tampa, FL 33601-0111
(813) 228-1111 ext. 39988
(863) 428-5927 (fax)
mjhornick@tecoenergy.com
George Lynch, DOE/HQ
(301) 903-9434
george.lynch@hq.doe.gov
Copyright Notice
Unless otherwise indicated, this information has
been authored by an employee or employees of the University of
California, operator of the Los Alamos National Laboratory
under Contract No. W-7405-ENG-36 with the U.S. Department of
Energy. The U.S. Government has rights to use, reproduce, and
distribute this information. The public may copy and use this
information without charge, provided that this Notice and any
statement of authorship are reproduced on all copies. Neither
the Government nor the University makes any warranty, express
or implied, or assumes any liability or responsibility for the
use of this information.
top of page
|