 |

home:
success stories:
Wabash River
A DOE cost-shared coal gasification demonstration project (now
in commercial operation) in West Terra Haute, Indiana.
Project Objective
To demonstrate utility repowering with a two-stage,
pressurized, oxygen-blown, entrained-flow IGCC system,
including advancements in the technology relevant to the use
of high-sulfur bituminous coal; and to assess long-term
reliability, availability, and maintainability of the system
at a fully commercial scale.
Technology/Project Description
The Destec, now E-Gas Technology™, process features an
oxygen-blown, continuous-slagging, two-stage, entrained flow
gasifier. Coal is slurried, combined with 95% pure oxygen, and
injected into the first stage of the gasifier, which operates
at 2600 ºF/400 psig. In the first stage, the coal slurry
undergoes a partial oxidation reaction at temperatures high
enough to bring the coal's ash above its melting point. The
fluid ash falls through a tap hole at the bottom of the first
stage into a water quench, forming an inert vitreous slag. The
syngas flows to the second stage, where additional coal slurry
is injected. This coal is pyrolyzed in an endothermic reaction
with the hot syngas to enhance syngas heating value and
improve efficiency.
The syngas then flows to the syngas cooler,
essentially a firetube steam generator, to produce
high-pressure saturated steam. After cooling in the syngas
cooler, particulates are removed in a hot/dry filter and
recycled to the gasifier. The syngas is further cooled in a
series of heat exchangers. The syngas is water scrubbed to
remove chlorides and passed through a catalyst that hydrolyzes
carbonyl sulfide into hydrogen sulfide. Hydrogen sulfide is
removed in the acid gas removal system using MDEA-based
absorber/stripper columns. A Claus unit is used to produce
elemental sulfur as a salable by-product. The "sweet" gas is
then moisturized, preheated, and piped to the power block. The
power block consists of a single 192-MWe General Electric
MS7001FA (Frame 7FA) gas turbine, a Foster Wheeler single-drum
heat-recovery steam generator with reheat, and a 1952 vintage
Westinghouse reheat steam turbine.
Results Summary: Environmental
-
The SO2 capture efficiency was
greater than 99%, keeping SO2 emissions
consistently below 0.1 lb/106 Btu and reaching as
low as 0.03 lb/106 Btu. Sulfur-based pollutants
were transformed into 99.99% pure sulfur, a highly valued
by-product—33,388 tons produced during the demonstration
period.
-
The NOx emissions were 0.15 lb/106
Btu, which meets the 2003 target emission limits for ozone
non-attainment areas, or 1.09 lb/MWh, which exceeds the New
Source Performance Standard of 1.6 lb/MWh.
-
Particulate emissions were below detectable
limits.
-
Carbon monoxide emissions, averaging 0.05 lb/106
Btu, were well within industry standards.
-
Coal ash was converted to a low-carbon vitreous
slag, impervious to leaching and valued as an aggregate in
construction or as grit for abrasives and roofing materials;
and trace metals from petroleum coke were also encased in an
inert vitreous slag.
Results Summary: Operational
-
Over the course of the demonstration, the IGCC
unit operated on coal for over 15,000 hrs, processed over
1.5 million tons of coal, and produced over 23 trillion Btu
of syngas and 4 million MWh of electricity.
-
Design changes in the first year included:
-
Using a less tenacious refractory in the
second-stage gasifier and changing the flow path geometry
to eliminate ash deposition on the second-stage gasifier
walls and downstream piping;
-
Changing to improved metallic candle filters
to prevent particulate breakthrough in the hot gas filter;
and
-
Installing a wet chloride scrubber and a COS
catalyst less prone to poisoning to eliminate chloride and
metals poisoning of the COS catalyst.
-
The second year identified cracking in the gas
turbine combustion liners and tube leaks in the heat
recovery steam generator (HRSG). Resolution involved
replacement of the gas turbine fuel nozzles and liners and
modifications to the HRSG to allow for more tube expansion.
-
The third year was essentially trouble free and
the IGCC unit underwent fuel flexibility tests, which showed
that the unit operated trouble free, without modification,
on a second coal feedstock, a blend of two different
Illinois #6 coals, and petroleum coke.
-
Overall thermal performance actually improved
during petroleum coke operation, increasing plant efficiency
from 39.7% to 40.2%.
-
In the fourth year, the gas turbine incurred
damage to rows 14 through 17 of the compressor causing a 3-
month outage. But over the four years of operation,
availability of the gasification plant steadily improved
reaching 79.1% in 1999.
Results Summary: Economic
-
The overall cost of the IGCC plant was $417
million, which equates to about $1,590/kW in 1994 dollars.
For an equivalent greenfield project the cost was estimated
at $1,700/kW. Capital cost estimates for a new 285 MWe (net)
greenfield IGCC plant incorporating lessons learned,
technology improvements, and a heat rate of 8,526 Btu/kWh
are $1,318/kW (2000$) for a coal-fueled unit and $1,260
(2000$) for a petroleum coke-fueled unit.
Project Summary
The Wabash River Coal Gasification Repowering Project
repowered a 1950s vintage pulverized coal-fired plant,
transforming the plant from a nominally 33% efficient, 90-MWe
unit into a nominally 40% efficient, 262-MWe (net) unit.
Cinergy, PSI’s parent company, dispatches power from the
project, with a demonstrated heat rate of 8,910 Btu/kWh (HHV),
second only to their hydroelectric facilities on the basis of
environmental emissions and efficiency.
Beyond the integration of an advanced
gasification system, a number of other advanced features
contributed to the high energy efficiency. These included: (1)
hot/dry particulate removal to enable gas cleanup without heat
loss, (2) integration of the gasifier high-temperature heat
recovery steam generator with the gas turbine-connected HRSG
to ensure optimum steam conditions for the steam turbine, (3)
use of a carbonyl sulfide (COS) hydrolysis process to enable
high-percentage sulfur removal, (4) recycle of slag fines for
additional carbon recovery, (5) use of 95% pure oxygen to
lower power requirements for the oxygen plant, and (6) fuel
gas moisturization to reduce steam injection requirements for
NOx control.
Over the four-year demonstration period starting
in November 1995, the facility operated on coal for more than
15,000 hours and processed over 1.5 million tons of coal to
produce more than 23 trillion Btu of syngas. For several of
the months, syngas production exceeded one trillion Btu. By
the end of the demonstration, the 262-MWe IGCC unit had
captured and produced 33,388 tons of sulfur.
Operational Performance
The first year of operation resolved problems with: (1) ash
deposition on the second stage gasifier walls and downstream
piping, (2) particulate breakthrough in the hot gas filter
system, and (3) chloride and metals poisoning of the COS
catalyst. Modifications to the second-stage refractory to
avoid tenacious bonds with the ash and to the hot gas path
flow geometry corrected the ash deposition problem.
Replacement of the ceramic candle filters with metallic
candles proved to be largely successful. A follow-on metallic
candle filter development effort ensued using a hot gas
slipstream, which resulted in im- proved candle filter
metallurgy, blinding rates, and cleaning techniques. The
combined effort all but eliminated downtime associated with
the filter system by the close of 1998. Installation of a wet
chloride scrubber eliminated the chloride problem by September
1996 and use of an alternate COS catalyst less prone to trace
metal poisoning provided the final cure for the COS system by
October 1997.
The second year of operation identified cracking
problems with the gas turbine combustion liners and tube leaks
in the HRSG. Replacement of the fuel nozzles and liners solved
the cracking problem. Resolution of the HRSG problem required
modification to the tube support and HRSG roof/penthouse floor
to allow for more expansion.
By the third year, downtime was reduced to
nuisance items such as instrumentation-induced trips in the
oxygen plant and high-maintenance items such as replacement of
high-pressure slurry burners every 40–50 days. In the third
year, the IGCC unit underwent fuel flexibility tests. The unit
operated effectively, without modification or incident, on a
second coal feedstock, a blend of two different Illinois #6
coals, and petroleum coke (petcoke). These tests added to the
fuel flexibility portfolio of the gasifier, which had
previously processed both lignite and subbituminous coals
during its earlier development. The overall thermal
performance of the IGCC unit actually improved during petcoke
operation. The unit processed over 18,000 tons of high-sulfur
petcoke and produced 350 billion Btu of syngas. There was a
negligible amount of tar production and no problems were
encountered in removing the dry char particulate despite a
higher dust loading. Exhibit 5-45 provides a summary of the
thermal performance of the unit on both coal and petcoke.
|
|
Exhibit 5-45
Wabash Thermal Performance Summary |
|
|
Design |
Actual |
|
|
|
|
Coal |
Coal |
Petcoke |
| Nominal Throughput, tons/day |
2,550 |
|
2,450 |
|
2,000 |
|
|
Syngas Capacity, 106
Btu/hr |
1,780 |
|
1,690 |
|
1,690 |
|
| Combustion Turbine, MW |
192 |
|
192 |
|
192 |
|
| Steam Turbine, MW |
105 |
|
96 |
|
96 |
|
| Auxiliary Power, MW |
35 |
|
36 |
|
36 |
|
| Net Generation, MW |
262 |
|
261 |
|
261 |
|
| Plant Efficiency,
% (HHV) |
37.8 |
|
39.7 |
|
40.2 |
|
| Sulfur Removal
Efficiency, % |
>98 |
|
>99 |
|
>99 |
|
|
The fourth year of operation was marred by a 3-month outage
due to damage to rows 14 through 17 of the gas turbine air
compressor. However, over the four years of operation,
availability of the gasification plant steadily improved,
reaching 79.1% in 1999. Exhibit 5-46 provides a summary of the
production statistics during the demonstration period.
|
|
Exhibit 5-46
Wabash River Coal Gasification Repowering Project
Production Statistics |
|
| Time Period |
On Coal (Hr) |
Coal Processed
(tons) |
On Spec. Gas
(106 Btu) |
Steam Produced
(106 Btu) |
Power Produced (MWh) |
Sulfur Produced
(tons) |
|
| Start-up 1995 |
505 |
41,000a |
230,784 |
171,613 |
71,000a |
559 |
| 1996 |
1,902 |
184,382 |
2,769,685 |
820,624 |
449,919 |
3,299 |
| 1997 |
3,885 |
392,822 |
6,232,545 |
1,720,229 |
1,086,877 |
8,521 |
| 1998 |
5,279 |
561,495 |
8,844,902 |
2,190,393 |
1,513,629 |
12,452 |
| 1999b |
3,496 |
369,862 |
5,813,151 |
1,480,908 |
1,003,853 |
8,557 |
|
| Overall |
15,067 |
1,549,561 |
23,891,067 |
6,383,767 |
4,125,278 |
33,388 |
|
|
aEstimate
bThe combustion turbine was unavailable from
3/14/99 through 6/22/99. |
Environmental Performance
The IGCC unit operates with an SO2 capture
efficiency greater than 99%.
As a result, SO2 emissions are
consistently below 0.1 lb/106 Btu of coal input,
reaching as low as 0.03 lb/106 Btu. Moreover, the
process transforms sulfur-based pollutants into 99.99% pure
sulfur, a highly valued by-product, rather than a solid waste.
Moisturizing the syngas in combination with steam
injection reduced NOx emissions to the 0.15 lb/106
Btu requirement established by EPA for existing plants in
ozone non-attainment areas. Because of the extreme particulate
filtration necessary for combustion of the syngas in a gas
turbine, particulate emissions were negligible, averaging
0.012 lb/106 Btu. Also, carbon monoxide emissions
were quite low, averaging 0.05 lb/106 Btu.
The ash component of the coal results in a
low-carbon vitreous slag, impervious to leaching and valued as
an aggregate in construction or as grit for abrasives and
roofing materials. Also, the trace metal constituents in the
petcoke were effectively captured in the slag produced.
Economic Performance
The overall cost of the IGCC demonstration plant was $417
million, which equates to about $1,590/kW in 1994 dollars. For
an equivalent greenfield project, allowing for additional new
equipment required, the installed cost was estimated at
$1,700/kW. Costs include engineering, permitting, equipment
procurement, project and construction management,
construction, start-up, and hiring and training personnel.
In the final report, the participant estimates
capital cost for a new 262-MWe greenfield IGCC plant
incorporating lessons learned, technology improvements, and a
heat rate of 8,250 Btu/kWh are $1,275/kW (2000$) for a coal-
fueled unit and $1,150 (2000$) for a petroleum coke-fueled
unit. In designing for petcoke, some equipment can be reduced
in size and some eliminated.
More recent data developed by DOE shows that a
285-MWe (net) coal-fired greenfield IGCC plant with a heat
rate of 8,526 Btu/kWh would cost $1,318/kW (2000$). A 291-MWe
(net) petroleum coke-fired IGCC unit with a 8,400 Btu/kWh heat
rate would cost $1,260/kW.
Annual fuel costs for the Wabash project ranged
from $15.3–19.2 million, with an annual availability of 75%
and using high-sulfur bituminous coal ranging from
$1.00–1.25/106 Btu ($22–27/ton). Non-fuel operation
and maintenance (O&M) costs for the syngas facility (excluding
the power block) was 6.8% of installed capital based on 75%
availability. O&M costs include operating labor and benefits,
technical and administrative support on and off site, all
maintenance, chemicals, waste disposal, operating services,
supplies, and 5% of the total O&M cost for betterments.
Projected O&M costs for a mature IGCC facility (including the
power block) are 5.2% of installed capital.
Commercial Applications
At the end of the demonstration in December 1999, Global
Energy, Inc. purchased Dynegy's gasification assets and
technology. Global Energy is marketing the technology under
the name “E-Gas Technology™.” The project is continuing to
operate in commercial service as Wabash River Energy, Ltd., a
subsidiary of Global Energy.
The immediate future for E-Gas Technology™
appears to lie with both foreign and domestic applications
where low-cost feedstocks such as petroleum coke can be used
and co-production options are afforded—bundled production of
steam, fuels/chemicals, and electricity. Integration or
association with refinery operations are examples. This
projection is born out in a recent announcement by the Port of
Port Arthur, Texas that they are entering into partnership
with Sabine Power I, Limited to build the world's largest
petroleum coke-fueled IGCC facility using E-Gas Technology™.
The Port estimates the cost of the facility at $1.75 billion;
construction jobs at 1,250; and permanent jobs at 200 to 250.
In the longer term, the technology has application to
repowering the aging fleet of existing domestic coal-fired
boilers, and new foreign and domestic coal-fueled capacity
additions. Factors favoring increased use of IGCC over time
are continued improvement in IGCC cost and performance,
projected increases in price differentials between coal and
gas, and continued importance placed on displacement of
petroleum in chemicals and fuels production.
Contacts
Phil Amick, Vice President
Global Energy, Inc.
1000 Louisiana St., Suite 3800
Houston, TX 77002
(713) 374-7252
(713) 374-7279 (fax)
pramick@globalenergyinc.com
George Lynch, DOE/HQ
(301) 903-9434
george.lynch@hq.doe.gov
Leo E. Makovsky, NETL
(412) 386-5814
leo.makovsky@netl.doe.gov
Copyright Notice
Unless otherwise indicated, this information has
been authored by an employee or employees of the University of
California, operator of the Los Alamos National Laboratory
under Contract No. W-7405-ENG-36 with the U.S. Department of
Energy. The U.S. Government has rights to use, reproduce, and
distribute this information. The public may copy and use this
information without charge, provided that this Notice and any
statement of authorship are reproduced on all copies. Neither
the Government nor the University makes any warranty, express
or implied, or assumes any liability or responsibility for the
use of this information.
top of page
|